Problem
Spotless were looking to increase the seating capacity at their Gladesville Offices To economically increase the seating capacity from /// to /// , provide 24 Hot Desks & convert existing hard wired System 2 & Other System workstations to softwiring
Solution
Spotless engaged Roberts Weaver Group to do preliminary sketch planning and trial fits. CFS responded to the proposed brief with a proposal to dismantle the existing work stations, from a 1800 × 2100 foot print to an 1800 × 1800 foot print, and re install in the new layout. The shortfall or positions was made up with reused workstations
Result
CFS won the work delivered the project over 2 weekends